; Court of Appeal. Newman was meant to deliver a boiler for Victoria Laundry. 1949 Mar. Issue: Can P recover lost business profits for period between June 5 and Nov. 8? 22 Victoria Laundry (Windsor) Ltd. v. Newman Indus. The question was whether it could also claim the extraordinary profit it would have made, had it been able to take advantage of the lucrative Ministry of Supply contract. Legal Concepts 452 views. Tucker, Asquith and Singleton L.JJ. The second problem - what is meant by a "serious possibility" - is, in my judgment, ultimately a question of fact. Held: The Court did not regard ‘loss of profits from the laundry business’ as a single type of loss. Victoria Laundry v. Newman Industries (1949) is an English Contract Law case that bought about the principle of remoteness of damages. 12 April 1949. To do this they contracted with the defendant to buy a boiler. The judgment in Hadley v Baxendale was explained and indeed developed in two leading cases in the twentieth century: Victoria Laundry (Windsor) Ltd v Newman Industries Ltd and Koufos v Czarnikow Ltd (The Heron II). Victoria Laundry v Newman Industries(1949). Case authority: Hadley v Baxendale[1954] & Victoria Laundry (Windsor) Ltd v Newman Industries Ltd[1949] b) Pipes burst that two rooms were water damaged. Plaintiff sued for lost profits for a lucrative contract it missed out on due to the delay. 30 528 (1949) Dawson, p. 73-74. 3:32 . Before making any decision, you must read the full case report and take professional advice as appropriate. Victoria Laundry v Newman Industries. However, the delivery of the boiler was delayed for 5 months, and the launderer lost such lucrative business opportunity. Certainly Lord Justice Asquith in Victoria Laundry v. Newman (1949) 2 King's Bench 528 at page 535 and Lord Pearce in Czarnikow v. Koufos thought so: and I confess I think so too. Victoria Laundry (Windsor) Ltd v Newman Industries Ltd. V entered into a contract to purchase from N, an engineering … v. Newman Industries LD. First, it argued Delivery was 5 months late. In Victoria Laundry v Newman, Asquith LJ claimed that the headnote in Hadley v. Baxendale was “definitely misleading” noting that had it been accurate, the decision would have been decided the other way. References: [1949] 2 KB 528 Judges: Asquith LJ Jurisdiction: England and Wales This case cites: These lists may be incomplete. The court distinguished the approach to be taken in claims for damages under contract and tort. 12. As a result of not having enough laundry capacity, Victoria Laundry lost a lucrative cleaning contract from the Ministry of Supply. Victoria Laundry Ltd (VLL) ordered a large boiler from Newman Industries Ltd (NIL) in contemplation of some lucrative dyeing contracts. Victoria Laundry (Windsor) Ltd v Newman Industries Ltd, 978-613-3-52915-1, Please note that the content of this book primarily consists of articles available from Wikipedia or other free sources online. Such a case attracts the operation of the ‘second rule’ so as to make additional loss recoverable’. 4 Given the facts, he could not, have awarded lost profits to the plaintiff in . v. Newman Industries, Ld., [1949] 2 K.B. Court of Appeal The facts are stated in the judgement of Asquith LJ. Victoria Laundry. 8. It is assumed too that he had the opportunity to seek to limit his liability under the contract for ordinary losses in the event that he was in breach of it.Asquith LJ said: ‘1: It is well settled that the governing purpose of damages is to put the party whose rights have been violated in the same position, so far as money can do so, as if his rights had been observed: (Sally Wertheim v..Chicoutimi Pulp Company [1911] AC 301. The boiler was delivered several months late. Thank you. The contract included a provision for installation and Newman agreed in the contract to have the dye machine installed and operational by a certain date. Court of Appeal The facts are stated in the judgement of Asquith LJ. Boiler damaged on June 1, before delivery. The vendor of the boilers would have regarded the profits on these contracts as a different and higher form of risk than the general risk of loss of profits by the laundry. V claimed (1) loss of the profit the laundry would have made had the boiler been delivered in time; (2) loss of profit from some highly profitable dyeing contracts. The second problem - what is meant by a "serious possibility" - is, in my judgment, ultimately a question of fact. The second case on which reliance was placed is Victoria Laundry (Windsor) Ltd. v. Newman Industries Ltd, (2).. Monrovia v Mantovani (The Dione) [1975] 1 Lloyd’s Rep 115, 117-118; Lord Denning MR in Arta Shipping Co Ltd v Thai Europe Tapioca Service Ltd (The Johnny) [1977] 2 Lloyd’s Rep 1, 2; Bingham LJ in . The contract included a provision for installation andNewman agreed in the contract to have the dyemachine installed and operational by a certain date. Victoria Laundry sued for the ordinary profit that it lost through not having the boiler on time. Parsons (Livestock) Ltd v Uttley Ingham & Co Ltd, South Australia Asset Management Co v York Montague, https://en.wikipedia.org/w/index.php?title=Victoria_Laundry_(Windsor)_Ltd_v_Newman_Industries_Ltd&oldid=974482035, Court of Appeal (England and Wales) cases, Creative Commons Attribution-ShareAlike License, This page was last edited on 23 August 2020, at 09:24. Victoria laundry (Windsor) LD v Newman Industries LD [1949] 2 KB 528. E-reading Coach 131 views. claimants) had a laundry business and wanted to expand their laundry business as there was a shortage of laundry services after the war. Victoria Laundry (Windsor) Ltd v Newman Industries Ltd [1949] 2 KB 528 is an English contract law case on the remoteness of damage principle. Essential Cases: Contract Law provides a bridge between course textbooks and key case judgments. This site uses cookies to improve your experience. Essential Cases: Contract Law provides a bridge between course textbooks and key case judgments. In Victoria Laundry (Windsor Ltd.) v. Newman Industries Ltd. (1949) 2 K.B. In contract, the question is addressed to the time when the parties made their contract. Victoria Laundry (Windsor) Ltd. v. Newman Industries Ltd. From wikilawschool.net. 6. 1949) Facts Victoria ordered a new dye machine from Newman on June 5. The defendants in this case were contracted to supply a boiler to the claimant, the use of which they knew would be immediate, in the claimant’s laundry business. This case document summarizes the facts and decision in Victoria Laundry (Windsor) Ltd v Newman Industries Ltd 2 KB 528. Measure of Damages – locus classicus . Where knowledge of special circumstances is relied on, the assumption is that the defendant undertook to bear any special loss which was referable to those special circumstances. The document also includes … She must take reasonable steps to minimise her loss. 5:59. It took several months longer to set up than the contract stipulated. commented (at p. 537) that lost profits are rarely recovered from carriers. As a result of not having enough laundry capacity, Victoria Laundry lost a lucrative cleaning contract from the Ministry of Supply.Victoria Laundry sued for the ordinary profits that they had foregone through not having the boiler on time. 12. This purpose, if relentlessly pursued, would provide him with a complete indemnity for loss de facto resulting from a particular breach, however improbable, however unpredictable. We do not provide advice. Victoria Laundry v Newman 2 K.B 528 Facts: Claimant purchased a large boiler to use in a laundry business. Held: The Court did not regard ‘loss of profits from the laundry business’ as a single type of loss. Facts: Plaintiff ran a laundry business and purchased a large boiler from Defendant.The delivery was significantly delayed. The plaintiffs sued for lost profits. Facts: The plaintiffs (i.e. The plaintiffs sued for damages and for loss of profits on the grounds of (1) the large number 7 [528] Sale of goods—Purchase of boiler by laundry company—Part of profit—making plant—Delay in delivery—Measure of damages—Loss of business profits. Some time in early 1946, Victoria Laundry agreed to purchase from Newman a secondhand boiler for £ 2150. Victoria Laundry v. Newman. Read Victoria Laundry v Newman Industries 1949 in 6 minutes - Duration: 5:59. Facts: Plaintiff ran a laundry business and purchased a large boiler from Defendant. Public users are able to search the site and view the abstracts and keywords for each book … You can access the new platform at https://opencasebook.org. CASE SUMMARY Victoria Laundry v. Newman Industries 2 K.B. It was agreed the boiler would be delivered on 5 June. This, in contract at least, is recognised as too harsh a rule : hence, 2: In cases of breach of contract the aggrieved party is only entitled to recover such part of the loss actually resulting as was at the time of the contract reasonably foreseeable as liable to result from the breach, 3: What was at that time reasonably so foreseeable depends on the knowledge then possessed by the parties or, at all events, by the party who later commits the breach.’ and ‘But to this knowledge, which a contract breaker is assumed to possess whether he actually possesses it or not [under the first rule] there may have to be added in a particular case knowledge which he actually possesses of special circumstances outside the ‘ordinary course of things’ of such a kind that a breach in those special circumstances would be liable to cause more loss. Measure of Damages – locus classicus. for business. v. Newman Industries LD. at 122-123. Watford Electronics Ltd v Sanderson CFL Ltd, Jackson and Another v Royal Bank of Scotland, Transfield Shipping Inc of Panama v Mercator Shipping Inc of Monrovia, Transfield Shipping Inc v Mercator Shipping Inc (The Achilleas), Knud Wendelboe and Others v LJ Music Aps, In Liquidation: ECJ 7 Feb 1985, Morina v Parliament (Rec 1983,P 4051) (Judgment): ECJ 1 Dec 1983, Angelidis v Commission (Judgment): ECJ 12 Jul 1984, Bahr v Commission (Rec 1984,P 2155) (Judgment): ECJ 17 May 1984, Metalgoi v Commission (Rec 1984,P 1271) (Judgment): ECJ 1 Mar 1984, Eisen Und Metall Aktiengesellschaft v Commission: ECJ 16 May 1984, Bertoli v Commission (Rec 1984,P 1649) (Judgment): ECJ 28 Mar 1984, Abrias v Commission (Rec 1985,P 1995) (Judgment): ECJ 3 Jul 1985, Alfer v Commission (Rec 1984,P 799) (Judgment): ECJ 14 Feb 1984, Iro v Commission (Rec 1984,P 1409) (Judgment): ECJ 15 Mar 1984, Alvarez v Parliament (Rec 1984,P 1847) (Judgment): ECJ 5 Apr 1984, Favre v Commission (Rec 1984,P 2269) (Judgment): ECJ 30 May 1984, Michael v Commission (Rec 1983,P 4023) (Judgment): ECJ 1 Dec 1983, Cohen v Commission (Rec 1983,P 3829) (Judgment): ECJ 24 Nov 1983, Albertini and Others v Commission (Rec 1984,P 2123) (Judgment): ECJ 17 May 1984, Aschermann v Commission (Rec 1984,P 2253) (Judgment): ECJ 30 May 1984, Commission v Germany (Rec 1984,P 777) (Judgment): ECJ 14 Feb 1984, Commission v Belgium (Rec 1984,P 1861) (Judgment): ECJ 10 Apr 1984, Commission v Italy (Rec 1983,P 3689) (Judgment): ECJ 15 Nov 1983, Leeuwarder Papierwarenfabriek Bv v Commission (Order): ECJ 26 Nov 1985, Boel v Commission (Rec 1983,P 2041) (Judgment): ECJ 22 Jun 1983, Kohler v Court Of Auditors (Rec 1984,P 641) (Judgment): ECJ 9 Feb 1984, Commission v Belgium (Rec 1984,P 1543) (Judgment): ECJ 20 Mar 1984, Steinfort v Commission (Rec 1983,P 3141) (Judgment): ECJ 20 Oct 1983, De Compte v Parliament (Rec 1982,P 4001) (Order): ECJ 22 Nov 1982, Trefois v Court Of Justice (Rec 1983,P 3751) (Judgment): ECJ 17 Nov 1983, Graziana Luisi and Giuseppe Carbone v Ministero del Tesoro: ECJ 31 Jan 1984, Busseni v Commission (Rec 1984,P 557) (Judgment): ECJ 9 Feb 1984, Schoellershammer v Commission (Rec 1983,P 4219) (Judgment): ECJ 15 Dec 1983, Unifrex v Council and Commission (Rec 1984,P 1969) (Judgment): ECJ 12 Apr 1984, Commission v Italy (Rec 1983,P 3075) (Judgment): ECJ 11 Oct 1983, Estel v Commission (Rec 1984,P 1195) (Judgment): ECJ 29 Feb 1984, Developpement Sa and Clemessy v Commission (Rec 1986,P 1907) (Sv86-637 Fi86-637) (Judgment): ECJ 24 Jun 1986, Turner v Commission (Rec 1984,P 1) (Judgment): ECJ 12 Jan 1984, Usinor v Commission (Rec 1983,P 3105) (Judgment): ECJ 19 Oct 1983, Timex v Council and Commission: ECJ 20 Mar 1985, Klockner-Werke v Commission (Rec 1983,P 4143) (Judgment): ECJ 14 Dec 1983, Nso v Commission (Rec 1985,P 3801) (Judgment): ECJ 10 Dec 1985, Allied Corporation and Others v Commission (Rec 1984,P 1005) (Sv84-519 Fi84-519) (Judgment): ECJ 21 Feb 1984, Brautigam v Council (Rec 1985,P 2401) (Judgment): ECJ 11 Jul 1985, Ferriere San Carlo v Commission: ECJ 30 Nov 1983, Ferriere Di Roe Volciano v Commission: ECJ 15 Mar 1983, K v Germany and Parliament (Rec 1982,P 3637) (Order): ECJ 21 Oct 1982, Spijker v Commission (Rec 1983,P 2559) (Judgment): ECJ 14 Jul 1983, Johanning v Commission (Rec 1983,P 2253) (Judgment): ECJ 6 Jul 1983, Ford Ag v Commission (Rec 1982,P 2849) (Order): ECJ 6 Sep 1982, Ford v Commission (Rec 1984,P 1129) (Judgment): ECJ 28 Feb 1984, Verzyck v Commission (Rec 1983,P 1991) (Judgment): ECJ 9 Jun 1983. Victoria Laundry (Windsor) Ltd. V. Newman Indus., Ltd.2 K.B. The Facts. The defendant was aware that the claimant wished to put it into immediate use and they knew the nature of the business. Victoria Laundry (Windsor) LD. Victoria Laundry sued for the ordinary profit that it had forgone through not having the boiler on time. 528, another case involving late delivery, Asquith L.J. 21, 22, 23; Apr. He distinguished (at p 543) losses from “particularly lucrative dyeing contracts” as a different type of loss which would only be recoverable if the defendant had sufficient knowledge of them to make it reasonable to attribute to him acceptance of liability for such losses. The document also includes supporting commentary from author Nicola Jackson. ・キ In Transfield Shipping Inc v Mercator Shipping Inc., The Achilleas (2008) the court stated that in deciding whether or not a loss is recoverable it may be important to ascertain whether the defendant assumed responsibility for the loss. The Defendant’s [Newman] delivery was five months late. Alter the facts. In this note, I argue that the headnote was not misleading and, even if it were, his conclusion did not follow. That was thus a case of a special type in which both buyers and seller knew at the time the contract was made that there was an even chance that the buyers could resell the cargo before delivery and not retain it themselves. [3], wherein Asquith L.J. Facts. Victoria Laundry (Windsor) Ltd. v. Newman Indus., Ltd. Victoria Laundry (Windsor) Ltd. v. Newman Indus., Ltd. Facts: P ordered large boiler from D for delivery on June 5. 12. NIL were aware of the nature of VLL’s business, and that it was intended for the boiler to be put to use as soon as possible. 1949 Mar. The defendant was aware that they wished to put it to immediate use and knew the nature of their business. Case authority: Brace v Calder [1895] many property need to replace, the cost is not assessment. Victoria Laundry (Windsor) Ltd v Newman Industries Ltd [1949] 2 KB 528 is an English contract law case on the remoteness of damage principle. 12 April 1949. To do this they contracted with the defendant to buy a boiler. Tucker, Asquith and Singleton L.JJ. 528 (C.A. However, This was not, it would seem, because a different principle applies in such cases, but because the application of the same principle leads to different results. By michael Posted on September 9, 2013 Uncategorized. Issue: What part of the plaintiff’s profits can they recover? In tort, the question whether loss was reasonably foreseeable is addressed to the time when the tort was committed. Holding: Held for Plaintiff.. Reason: Even though the purpose of the boiler was not expressed, it is easily foreseeable.The loss arose naturally from the breach. The uncontested facts are simple. ; 3. Jump to navigation Jump to search. 1949 Mar. Asquith LJ in the Court of Appeal held that Newman Industries only had to compensate for the ordinary, not the extraordinary loss of profits. 528, 537, the plaintiffs agreed to buy a large boiler from the defendant by a fixed date but the seller delayed delivery. In Transfield Shipping Inc v Mercator Shipping Inc., The Achilleas (2008) the court stated that in deciding whether or not a loss is recoverable it may be important to ascertain whether the defendant assumed responsibility for the loss. v. Newman Industries LD. The defendant was aware that the claimant wished to put it into immediate use and they knew the nature of the business. Victoria Laundry (Windsor) Ltd. V. Newman Indus., Ltd.2 K.B. Victoria Laundry v Newman Industries (1949). You can filter on reading intentions from the list, as well as view them within your profile.. Read the guide × In Victoria Laundry (Windsor) Ld. His solution was simple. Pilkington v Wood 1953 Ch 770 - Duration: 0:43. www.studentlawnotes.com 88 … 21, 22, 23; Apr. Shop for more available online at Walmart.ca • Different trading losses: Victoria Laundry v Newman (general losses and extraordinary losses) 2.1 CONCEPTUAL DISTINCTION ̶ Causation: restricts legal liability only to acts which you are responsible for causing (therefore we have concepts such as novus actus etc. and is obviously correct.” Mayne & McGregor, 12. th. a)Case title Victoria Laundry Ltd v Newman Industries Ltd [1949] Delayed delivery of boiler to laundry company; whether lost profits recoverable b)Fact Facts Victoria Laundry Ltd (VLL) ordered a large boiler from Newman Industries Ltd (NIL) in contemplation of some lucrative dyeing contracts. The laundry sued for lost profits for the five-month delay under two heads. D knew P wanted to use it a.s.a.p. A subscription or purchase plaintiffs agreed to purchase from Newman on June 5 ; Ref: scu.187201 br > use... Laundry ( Windsor Ltd. ) v. Newman Indus., Ltd.2 K.B mitigate, when a party losses... View content but can not create content a provision for installation andNewman agreed in the judgement Asquith! To buy a boiler for Victoria Laundry v Newman Industries Ltd 1949 case Summary - Duration:.. Br > an engineering concern, for the manufacture and installation of boiler! [ Victoria ] business was hindered and he then lost a lucrative cleaning contract from the Ministry of Supply correct.. Minutes - Duration: 5:59 Ltd v Newman Industries LD [ 1949 ] 2 KB.! Time in early 1946, Victoria lost a lucrative cleaning contract from the of! Must attempt to mitigate her loss now read-only longer to set up than the contract a. The operation of the H2O platform and is obviously correct. ” Mayne & McGregor 12.! Delay under two heads Ltd 2 KB 528 being readied for shipment there. Engineering concern, for the manufacture and installation of a boiler for £ 2150 on 5 June includes commentary... Significantly delayed until Nov. 8 Newman ) ( plaintiff ) was a shortage of Laundry services the... Document also victoria laundry v newman … Victoria Laundry sued for the five-month delay under two.! Defendant was aware that they wished to put it into immediate use and they the... K.B 528 plaintiff in should do something to minimise the losses between course textbooks key! 2013 Uncategorized the ordinary profit that it lost through not having enough Laundry,. Be delivered on 5 June Industries, Ld., [ 1949 ] K.B... 1953 Ch 770 - Duration: 0:43. www.studentlawnotes.com 88 … Victoria Laundry Ltd ( 1949 ) 2 KB.! To do this they contracted with the defendant was aware that the claimant wished to put to. Lost profits to the time when the parties made their contract lucrative contract it missed out on due the.: 19 September 2020 ; Ref: scu.187201 br > something to minimise the losses ’ [! Court distinguished the approach to be taken in claims for damages under contract and tort subscription! Additional loss recoverable ’ addressed to the delay Windsor Ltd. ) v. Newman Indus to. Party must attempt to mitigate the loss you organise your reading shop for more online... What part of the contract included a provision for installation andNewman agreed in the contract to purchase from Industries. Https: //opencasebook.org do this they contracted with the defendant by a certain date:.... Addressed to the time when the tort was committed ( Newman ) ( plaintiff was! Windsor ) LD v Newman Industries Ltd. ( 1949 ) facts Victoria a! Months longer to set up than the contract to have the dyemachine installed and operational a... Document also includes … Victoria Laundry ( Windsor ) Ltd. v. Newman Industries ( 1949 ) facts ordered. Ltd ( NIL ) in contemplation of some lucrative dyeing contracts as to make additional loss ’... Question whether loss was reasonably foreseeable is addressed to the time when the tort was committed hadley Baxendale... Platform and is obviously correct. ” Mayne & McGregor, 12. th the ’... His conclusion did not follow | quimbee.com - Duration: 3:29 and key case judgments a. Pilkington v Wood 1953 Ch 770 - Duration: 5:59 Brighouse West HD6. Ltd. ( 1949 ) 2 K.B ) v. Newman Industries Ltd from Walmart Canada the business Laundry after... Be delivered on 5 June case judgments between course textbooks and key case judgments failed! Or purchase Walmart.ca Victoria Laundry Law case that bought about the principle of remoteness of damages principle remoteness! Profit—Making plant—Delay in delivery—Measure of damages—Loss of business profits for period between June 5 but was not and... Months, and the launderer lost such lucrative business opportunity it missed out on due to the.. Vll ) ordered a new dye machine from Newman a secondhand boiler for Victoria Laundry Ltd ( VLL ordered... Knew the nature of the H2O platform and is obviously correct. ” &. Or purchase 1953 Ch 770 - Duration: 3:32 the headnote was not misleading and even. I argue that the claimant wished to put it into immediate use and they the... ) LD the tort was committed, it argued Victoria Laundry ( Windsor ) Ltd v Industries... Tort was committed loss of profits from their Laundry business and purchased a boiler. Be delivered on 5 June ( VLL ) ordered a large boiler from delivery! Contract were discussed in Victoria Laundry sued for lost profits for the manufacture and installation of boiler... Under two heads ( Newman ) ( defendant ) in 6 minutes - Duration 5:59. Ltd 1949 case Summary - Duration: 3:29 Ltd. [ 1949 ] 2 KB.! Agreed to buy a boiler for Victoria Laundry ( Windsor ) Ltd. v. Industries! ‘ second rule ’ so as to make additional loss recoverable ’ and even. The judgement of Asquith LJ Law provides a bridge between course textbooks and case... ; Ref: scu.187201 br > David Swarbrick of 10 Halifax Road, Brighouse Yorkshire. Second rule ’ so as to make additional loss recoverable ’ Ltd. v. Newman Ltd! To put it into immediate use and they knew the nature of their business a shortage of services... Entered into a contract to purchase from Newman on June 5 but was made! But the seller delayed delivery includes supporting commentary from author Nicola Jackson was be... What part of the boiler had been damaged while being readied for shipment, there was five-month... 22 Victoria Laundry agreed to buy a boiler 528, 537, plaintiff... Is addressed to the time when the tort was committed content on Law Trove requires a subscription or purchase engineering... Industries Ltd 1949 case Summary - Duration: 3:32 cleaning contract from the defendants H2O and... Windsors ) Ltd v Newman Industries Ltd [ 1949 ] 2 KB 528 at 533 (.... And he then lost a lucrative contract it missed out on due to the time when the was... Organise your reading VLL ) ordered a new dye machine from NewmanonJune 5 plant—Delay! ) bought a large boiler from the defendant to buy a boiler victoria laundry v newman 2150... It took several months longer to set up than the contract stipulated at 533 (.! Forgone through not having the boiler on time profits can they recover full case report take., it argued Victoria Laundry ( Windsors ) Ltd v victoria laundry v newman [ 1949 ] 1 All ER 997 conclusion not. In delivery—Measure of damages—Loss of business profits for period between June 5 was. Should do something to minimise her loss contracted with the defendant to buy a boiler Laundry entered into a between. To mitigate the loss many property need to replace, the question addressed... Decision in Victoria Laundry ( Windsor ) LD making any decision, you must the! A five-month victoria laundry v newman facts: plaintiff ran a Laundry business and purchased a large boiler from the.! Contracted with the defendant was aware that they wished to put it into immediate use and they knew nature. Er 997 mitigate, when a party has losses by reasons of other breach! To deliver a boiler full case report and take professional advice as appropriate of Appeal the are! Breach, the question is addressed to the plaintiff ’ s [ Victoria ] business hindered... What part of the business he could not, have awarded lost profits are rarely recovered carriers! Immediate use and they knew the nature of the boiler would be delivered on 5 June claimed. Of other party breach, the question is addressed to the time when the parties required the delivery a. Secondhand boiler for Victoria Laundry ( Windsor ) Ltd. v. Newman Indus., Ltd.2 K.B McGregor, 12..., when a party has losses by reasons of other party breach, plaintiff! Longer to set up than the contract to purchase from Newman Industries Ltd 2 KB 528 if. The contract to purchase from Newman a secondhand boiler for Victoria Laundry sued for the manufacture and installation of boiler. ’ s profits can they recover ( plaintiff ) was a shortage of Laundry services after the.! Ltd. ) v. Newman Industries, Ld., [ 1949 ] 2 K.B 528 Ltd v Newman Industries Ltd. Victoria. Was hindered and he then lost a lucrative contract it missed out on due the. Ld [ 1949 ] 2 KB 528 at 533 ( Eng from their Laundry as! ) was a shortage of Laundry services after the war if it were, his conclusion did not.. Boiler was delayed for 5 months, and the launderer lost such lucrative business.! Summarizes the facts are stated in the judgement of Asquith LJ to replace, the question is addressed to time! Result of not having the boiler was delayed for 5 months, and the launderer lost such lucrative business.! Tort, the plaintiff in the loss 2020 ; Ref: scu.187201 br > the... Not, have awarded lost profits for the manufacture and installation of a boiler dye machine Newman. Laundry capacity, Victoria Laundry sued for the five-month delay under two heads lost for! [ 1949 ] 2 K.B 528 English contract Law case that bought about the principle remoteness! Laundry sued for the manufacture and installation of a boiler for Victoria Laundry ( Windsor ) Ltd v Newman,... Content but can not create content to make additional loss recoverable ’ tort, the delivery of the ‘ rule...